Chapter 8 Answer Key
8.1: Create the Project Network Diagram
Questions: Project Networks
1. C – Conditional statements are allowed.
2. Longest
3. B – I-node, J-node
4. A – Early Start, Early Finish
5. A – Slack or Float; B – Late Finish; C – Late Start
6. B – Burst Activity
7.
Exercise 1
Critical path is highlighted in yellow.
Exercise 2
Critical path is highlighted in yellow.
1. C – A–>E–>G–>H
Exercise 3
Critical path is highlighted in yellow.
1. A – It has zero slack; B – Its Early Start is 57 time units
2. B – The project will be 4 days late
8.2: Advanced Network Diagrams
Matching: Advanced Project Networks
I – The finish time of one task is dependent on another task finishing
B – The amount of time that a task in a project network can be delayed without causing a delay to subsequent tasks
G – The start of one task is dependent on another task finishing
A – The amount of time that a task in a project network can be delayed without causing a delay to the project completion date
J – The finish of one task is dependent on another task starting
C – Doesn’t use up resources and doesn’t add any direct costs to our project. Adds time to forward pass calculations
D – Our project is ahead of schedule
H – The start of one task is dependent on another task starting
E – Our project is behind schedule
F – Doesn’t use up resources or time, and doesn’t add any direct costs to our project. Used to mark important events