Resourcing Schedule for 2024

A project resourcing schedule lists project requirements and matches them with available resources. A typical annual resourcing schedule details the engagement’s size. It includes a list of the audit activities planned for that year, information about the number of hours and personnel required to complete each activity, and a timeframe for completion.

Buy and Large’s resourcing schedule for the current year (2024) is presented below. This resourcing schedule is typical of such schedules.

Table: Buy and Large’s resourcing schedule for 2024.
Activity Title Engagement Size Hours Personnel Assigned Scheduled Time of Year
Cybersecurity Management Audit Large 825 hours 5 Q1 (Jan – Mar)
Regulatory Compliance Framework Audit Large 825 hours 5 Q2 (Apr-Jun)
Financial Reporting Systems Audit Medium 550 hours 4 Q1 (Jan – Mar)
Market Dynamics and Adaptability Audit Medium 550 hours 3 Q2 (Apr-Jun)
Economic Impact Assessment Medium 550 hours 3 Q3 (Jul – Sep)
IT Infrastructure Review Small 330 hours 2 Q3 (Jul – Sep)
Supply Chain Efficiency Review Small 330 hours 2 Q4 (Oct-Dec)
Privacy Policy Implementation Review Small 330 hours 2 Q4 (Oct-Dec)
Cybersecurity Consulting Project Consulting 330 hours 2 Q1 (Jan – Mar)
Supply Chain Strategy Consulting Consulting 330 hours 2 Q3 (Jul – Sep)
Administrative Tasks N/A 500 hours Varies Throughout the Year
Continuing Professional Education (CPE) N/A 300 hours Varies Throughout the Year

 

License

Icon for the Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License

Internal Auditing: A Practical Approach Copyright © 2024 by Amit M. Mehta is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License, except where otherwise noted.

Share This Book